Projects

The City of Coos Bay does municipal construction projects to maintain and improve the city and better serve residents.

In 2016, the City broke ground for an expansion and upgrade to the existing Wastewater Treatment Plant No. 2, located in Empire at S Empire Boulevard and Fulton Avenue. This project will replace and upgrade the current treatment plant, provide better water quality and be able to meet future needs of the community.


FAQs

View All


Wastewater Treatment Plant No. 2 Expansion and Upgrade

WWTP2 Panorama

The City of Coos Bay is constructing an expansion and upgrade to the existing Wastewater Treatment Plant No. 2. Plant 2 treats sewage for western Coos Bay, including Empire, Barview, and Charleston. The existing plant is over 50 years old and will be upgraded with current technology, new Sequencing Batch Reactor treatment basins, and UV disinfection. The plant will provide better water quality and the ability to meet current and anticipated DEQ standards for the future needs of the community. The new facility will be built at 490 Fulton Avenue, just north of the Lighthouse Market. The plant is designed with capacity for population growth for a minimum of 20 years. It will be built so that modules may be added as needed for future expansion.

M.A. Mortenson Construction and their local construction partners, Billeter Marine and Kyle Electric, will build the upgrades. CH2M in partnership with the local engineering firm SHN Engineers & Geologists Inc. designed the new plant.

A 1% interest DEQ State Revolving Fund wastewater loan with a $500,000 grant is funding the project. The total cost of the construction improvements is budgeted at $24,531,820.

The project started in September 2016 and is expected to be finished in late summer 2018. Piping connecting the outfall to the new plant site was installed in the fall of 2016 during the road project to reduce traffic delays for residents. Excavation will begin January 10, 2017 for the main basins.

Top

Project Schedule and Current Status

Top

Photos showing progress of the construction

2-8-17 Sequencing Batch Reactor basin

2/8/17: Sequencing Batch Reactor basin.  View to the west from Marple Street up above the construction. This is the big basin dug for the Sequencing Batch Reactor. The brown object is a tree trunk that was dug up during excavation. Most of the basin has been dug down to undisturbed soils, but there is some old fill on the site that still needs to be removed.

 

2-8-17 Sequencing Batch Reactor basin with filter

2/8/17: Sequencing Batch Reactor basin. View to the east from Empire Blvd. This shows how deep the basins are. The white is filter fabric to help hold the bank during construction. There has been a lot of rain this week and the site is pretty muddy, but the contractor has begun to put rock into the excavated basins to form the foundation support. The rock will reduce the mud and make it easier to work.

Top

Construction impacts, including detours and expected delays

No traffic impacts are expected at this time. 

The limits of the project will include 490 Fulton Avenue, Fulton Avenue west of S. Empire Blvd, and Fulton Avenue between S. Empire Blvd and Marple Street.

Trucks and equipment will enter the plant site from S. Empire Blvd and from Marple Street. They will exit onto Fulton Avenue and Marple Street. The roads adjacent to the plant site will be open to traffic at all times, but there may be brief delays with flaggers while equipment enters or leaves the site. Pedestrian access will be closed or limited on the east side of S. Empire Blvd.

Fulton Avenue west of S. Empire Blvd will be heavily traveled by equipment and trucks. City staff will be requesting the closure of this section of Fulton during construction hours at the February 7, 2017 Council meeting at 7:00 pm.

Top

Staff leading the WWTP2 project.

Jan Kerbo

Jan Kerbo, PE, Resident Project Representative

Jan is the representative for the City for the WWTP2 project.

jkerbo@coosbay.org

541-269-1181 ext. 2206

Bob_Sanguinetti Bob Sanguinetti, Project Manager for Mortenson Construction

Bob serves as Mortenson’s onsite representative in managing the construction of the project from all levels (safety, schedule, budget, and quality) and acts in the interest of the City of Coos Bay as their Construction Manager.

   
Top